Rumdel Construction has been awarded a Contract for the Construction of the Road from Likalaneng to Thaba Tseka, km 0 to km 31. (Lot 1), and started in June 2006.
This contract constitutes the first phase of the upgrading of the 90 km road to a surfaced standard and will be carried out over the next 18 months. The contract cludes some 130 000 m3 crushing, 260 000m2 of asphalt surfacing, 130 000m3 earthworks, 215 000m3 hard excavation as well as the construction of a bridge over the Senqunyane river.
|